Project Description:
The Manhattan II Apartments consists of two (2) five story apartment buildings
with one level of below grade parking. The building contains a common
parking garage below grade, leasing office, lounge, fitness center and 134
apartment units. The structure is cast-in-place concrete foundations on drilled
piers with post-tensioned elevated slabs at grade and one story above grade.
Above the concrete podium are two wood framed, four story buildings. Partitions in the concrete structure are metal framing and CMU. The exterior
is stone, brick, metal panel and stucco veneer with vinyl windows and a TPO membrane roof. Decorative balcony railings, landscaped terraces,
concrete pavers, metal planters, etc. for each building, landscape/hardscape connection between the buildings, associated curb, gutter, sidewalks
and landscape/streetscape make up the exterior.
CURRENT PROGRESS
• Building Permit Approval Anticipated March 29, 2011
• Drilling for Shoring Piles
• Mass Excavation In Progress
• Subcontractor’s Mobilizing Staging Area
• Abandon Existing Utilities on Site
PLANNED FOR APRIL 2011
• Continue Soilder Piles and Lagging Installation
• Mass Excavation Activities will continue in April
• Street Cuts to Abandon Utilities
SCHEDULE MILESTONES
• Shoring Installation – Complete Early April
• Mass Excavation – Complete End of April
• Concrete Foundation – Start in May
• Concrete Podium – Start in July
• Wood Structure – Start in August
• Exterior Envelope – Start in October
• Interior Construction – 40 weeks
• Substantial Completion – Building 1 & Garage – April 13, 2012
• Substantial Completion – Building 2 – June 5, 2012
• Certificate of Occupancy – June 15, 2012
QUALITY/SAFETY ISSUES
• Additional Signage at Perimeter of Site added for Stop Signs at Bassett & 18th Streets
• Street Sweeping and Dust Control as Necessary

Leave A Response »